Extreme Networks Consolidated Hardware Guide 8-3
Installing the Alpine 3800 Series AC Power Supply
module has passed its POST and is operational, each I/O module then performs its own
POST.
Note: See Chapter 9 for more information about switch management module
LED activity and Chapter 10 for more information about I/O module LED activity.
Installing the Alpine 3800 Series AC Power
Supply
This section describes how to install an AC power supply for either the Alpine 3808 or
the Alpine 3804 switch. The Alpine 3802 switch power supply is preinstalled at the
factory. The power supplies for the Alpine 3808 switch are inserted into the front of the
chassis. The power supplies for the Alpine 3804 switch are inserted into the lower rear
of the chassis.
Note: Mount the chassis in a rack before installing any switch components.
To install the Alpine 3808 and Alpine 3804 AC power supplies:
1 Attach the ESD strap that is provided to your wrist and connect the metal end to the
ground receptacle that is located on the top-right corner of the switch front panel.
2 Remove the blank faceplate that is covering the power supply bay.
3 Ensure that the power supply is oriented correctly for either the Alpine 3808 or
Alpine 3804 using the text on the front of the power supply, and ensure that the
ejector/injector lever is open, as shown in Figure 8-1 and Figure 8-2.
Caution: When you insert a power supply, use one hand to support the power
supply from the bottom and the other hand to hold the central handle on the
front of the power supply. Do not use just the ejector/injector lever to insert a
power supply.
4 Use the central handle to guide the first power supply into the power supply bay.